Skip to Main Content
Lawyers in Edinburgh
Solicitors in Edinburgh
Family Solicitors/Lawyers in Edinburgh

Latest news and insights

Gillespie Macandrew to Sponsor First-Ever ‘Guard of Honour’ at the 2025 Howden Melrose Sevens

Gillespie Macandrew is proud to announce that our firm will sponsor the first-ever 'Guard of Honour' at the historic 2025 Howden Melrose Sevens tournament.

Easter Bunny Blues: Navigating Pet Custody

Rachael Burke explains how Pet Custody unfolds when a relationship breaks down.

ScotLand Matters Podcast: 20 Years at SLE

Robert Scott-Dempster and David Johnston join SLE's Chief Executive Sarah-Jane Laing's as she marks her 20th year at the organisation.

Viking Energy | Wind Farm Development

Published: 16 May 2022
Time to read: 2 mins

We act for Viking Energy Wind Farm LLP in respect of the major wind farm development on mainland Shetland.

The project has Consent from the Scottish Ministers for the installation of 103 wind turbines with a total capacity of circa 450 Megawatts. It is expected to be one of the largest onshore windfarms in the UK with the highest annual electricity output when construction is completed and it begins generating.

We have provided advice and support to this ground-breaking remote island wind project for over 10 years, building and adapting the appropriate team for each aspect and stage of the project.

View Full Case Study Download

Skills applied include:

  • Corporate;
  • Crofting;
  • Dispute Resolution;
  • Energy Regulation and support mechanisms;
  • Land assembly;
  • Planning; and
  • Rural tenure.

This has included:

  • Investigating complex estate titles, putting in place 20+ landowner agreements and purchase of specific areas of land;
  • Acting on behalf of the client together with senior and junior counsel throughout the challenge of the s36 Planning Consent, by way of judicial review, through the Inner and Outer House of the Court of Session and up to the Supreme Court where the consent for the development was ultimately upheld;
  • Transfer of project interests to appropriate corporate vehicles;
  • Providing advice in relation to the application to vary the existing s36 Planning Consent to enable the development to proceed with increased wind turbine tip height and increased rotor diameter;
  • Preparation and submission to the Scottish Land Court of a Scheme for Development to facilitate development on an extensive area (> 10,000 ha) of croft land, involving multiple common grazings and several hundred crofting interest. This was the largest application under the relevant legislation and required forensic consideration of the legislation and the various impacts of the windfarm on crofters’ interests, and providing a scheme to compensate them accordingly. The Scottish Land Court granted approval of the Scheme for Development in September 2018;
  • Advice in relation to Contracts for Difference;
  • Securing the approval of the Scottish Land Court of a second Scheme for Development to facilitate development on an extensive area of croft land in accordance with the varied Scottish Government consent; and
  • Advising in relation to varying land agreements to enable commencement of works, discharge of planning conditions, interaction with third parties in relation to connection and delivery routes.

 

Go Back

SUBSCRIBE

To receive regular updates like this one, you can sign up to our bulletins, and we will provide updates on the issues that matter to you.

SUBSCRIBE NOW

Get in touch

Contact us to find out how we can help you.

Get in touch

Lawyers in Edinburgh
Solicitors in Edinburgh
Family Solicitors/Lawyers in Edinburgh

Find a lawyer

If you are looking for a specific member of our team, you can search for them by their name here. You can also search for your regular contact by their area of expertise using the buttons below.

Visit the ‘Our People’ page for more ways to search if you can’t find who you’re looking for.